What should a tradesperson contract include?
A tradesperson contract should, as a minimum, describe who the parties are, what is to be done, which materials are to be used, what the work costs, when it is to be finished and how payment is to be made.
The contract should also explain how changes, additional work, delays, documentation and any faults are to be handled.
The bigger the project, the more important the details. A contract that only says "bathroom renovation - 250,000 kr" gives too little information if the parties later disagree about tiles, electrical work, fittings, the schedule or waste handling.
A good contract protects both the customer and the tradesperson. The customer gains control over what is to be delivered, while the tradesperson gets a clear description of what the business has actually committed to.
The Norwegian Consumer Council (Forbrukerrådet) recommends that you always use a written contract when you order tradesperson services. That makes it easier to establish what you have agreed if a disagreement arises. See the Consumer Council's guidance on using a tradesperson.
This article provides general information and is not a substitute for individual legal advice.
In short
A tradesperson contract should include:
- Names and contact details of both parties
- The business's organisation number
- The address where the work is to be carried out
- A detailed description of the work
- Drawings, measurements and other attachments
- The chosen materials and products
- Work that is not included
- Fixed price, price estimate or hourly rate
- Total price including VAT
- Start and completion dates
- Milestones and payment plan
- Responsibility for materials, applications and subcontractors
- Rules for changes and additional work
- Consequences of delay
- Requirements for quality and workmanship
- Documentation to be delivered
- Procedure for the final inspection
- Handling of faults and complaints
- Insurance and liability for damage
- How any dispute is to be handled
- Date and signature of both parties
Why is a written contract important?
Oral agreements can be binding, but are often difficult to document.
The customer may remember that the price included materials, while the tradesperson believes the materials were to be invoiced separately. The tradesperson may believe the customer ordered extra work orally, while the customer understood the work to be part of the original agreement.
A written contract reduces the risk of such misunderstandings.
The contract answers four basic questions:
- What is the tradesperson to deliver?
- When is it to be delivered?
- What is the customer to pay?
- What happens if something does not go as agreed?
The contract should be drawn up before the work starts. Quotes, drawings and later change orders should be attached and treated as part of the agreement.
Which law applies?
When a private individual buys repairs, maintenance, installation, conversion or other tradesperson services from a business, the Consumer Craftsman Services Act (håndverkertjenesteloven) normally applies.
Among other things, the Act regulates:
- How the work is to be carried out
- The tradesperson's duty to give guidance and to advise against work
- Additional work
- Delay
- Faults and defects
- Price and price estimates
- Itemised bills
- Payment
- Complaints
The Act cannot simply be departed from to the consumer's disadvantage. The contract can give the customer better rights than the Act, but normally cannot remove mandatory consumer rights.
When a new home is built or bought, the Housing Construction Act (bustadoppføringslova) and other contract forms apply as a general rule. You should therefore choose a contract that suits the specific type of project. See the relevant consumer contract forms from Standard Norge.
1. The parties to the agreement
The contract must clearly identify the customer and the tradesperson's business.
For the customer, the contract should include:
- Full name
- Address
- Telephone number
- Email address
- Any co-customer or co-owner
- Who is authorised to approve changes
For the tradesperson, the contract should include:
- The business's legal name
- Organisation number
- Business address
- Telephone number and email
- Contact person
- Project manager
- Any main contractor
- Any subcontractors
The business name and organisation number should match the information in the business register of the Brønnøysund Register Centre (Brønnøysundregistrene).
It should also state who has authority to enter into agreements on behalf of the business. This is particularly important if several employees, project managers or subcontractors are involved.
2. Address and project information
The contract should identify the project clearly.
Include:
- The address where the work is to be carried out
- Type of home
- Apartment number or section number
- Which rooms or areas the work covers
- Any property designation
- Contact person on site
- Access, key arrangements and parking
- Rules from the co-ownership association (sameie) or housing cooperative (borettslag)
- Permitted working hours
- Practical limitations
If the customer will not be living in the home during the work, the contract should describe how keys, access, the alarm and supervision are to be handled.
3. Detailed description of the work
The description of the work is usually the most important part of the contract.
Avoid general wording such as:
- "Renovate bathroom"
- "Paint the apartment"
- "Build a terrace"
- "Install kitchen"
- "Carry out carpentry work"
Instead, describe the work step by step.
For a bathroom renovation, the description of the work may include, among other things:
- Removal of existing fittings and surfaces
- Removal and sorting of waste
- Inspection of the subfloor and walls
- Building up the floor and walls
- Plumbing work
- Electrical work
- Membrane
- Tiling
- Painting the ceiling
- Installation of fittings
- Installation of the shower and toilet
- Ventilation
- Grouting
- Cleaning
- Testing and final inspection
- Documentation
Also describe what the customer expects as the finished result. "Plasterboard wall installed" is not the same as a finished wall that has been filled, painted and fitted with trim.
4. Drawings, measurements and attachments
Drawings, photos, quotes, product lists and descriptions should be numbered and attached to the contract.
Example:
- Attachment 1: Description of the work
- Attachment 2: Floor plan
- Attachment 3: Product and material list
- Attachment 4: Price quote
- Attachment 5: Progress plan
- Attachment 6: Payment plan
- Attachment 7: Requirements for final documentation
The contract should also explain which documents take precedence if they contradict each other.
One example of an order of precedence could be:
- The signed contract
- Approved change orders
- The description of the work
- Drawings
- The product and material list
- The original quote
- Other written communication
The order must be adapted to the project. The point is that the parties should know which document applies if two attachments contain different information.
5. Work that is not included
The contract should describe both what the tradesperson is to do and what is not included.
Examples of work that may be left out:
- Electrical work
- Plumbing work
- Painting
- Filling
- Application to the municipality
- Technical design
- Calculations by a structural engineer
- Demolition
- Removal of waste
- Scaffolding or lift
- Moving furniture
- Final cleaning
- Delivery of materials
- Repair of hidden damage
A clear list of exclusions reduces the risk of the customer believing something is included when it is not.
6. Materials and products
The contract should explain which materials and products are to be used.
Include:
- Manufacturer
- Product name
- Model
- Item number
- Dimensions
- Colour
- Finish
- Quality grade
- Quantity
- Price
- Who orders
- Who pays
- Who receives the delivery
- Who is responsible for incorrect orders
- How surplus materials are handled
Avoid wording that only says "standard materials" or "tiles as agreed".
If the product has not been chosen when the contract is signed, you can agree on a budget or a price range.
Example:
The contract price includes tiles with a purchase price of up to [amount] kr per m². If the customer chooses more expensive tiles, the price difference and any additional installation costs must be approved in writing before ordering.
It should also state whether the tradesperson may switch to an equivalent product if the agreed product is not available. Such a switch should be approved in writing.
7. Who buys the materials?
If the tradesperson buys the materials, the contract should describe:
- Any mark-up on materials
- Costs for ordering and transport
- Who handles complaints
- When the materials become the customer's property
- What happens on cancellation
- How unused materials are handled
If the customer buys the materials, the contract should explain:
- Who takes the measurements
- Who prepares the material list
- Who checks the product
- Who bears the cost of incorrect orders
- What happens if the materials are delivered late
- Whether the tradesperson guarantees materials chosen by the customer
Incorrect or late delivery of the customer's materials can affect both progress and price. This should be clarified in advance.
8. Price and pricing model
The contract must state whether the work is carried out at:
- Fixed price
- Price estimate
- Hourly rate
- Unit price
- A combination of several pricing models
Fixed price
For a fixed price, the contract should state:
- Total price including VAT
- Which work the fixed price covers
- Which materials are included
- Which costs come in addition
- The assumptions the fixed price is based on
Example:
The agreed fixed price is [amount] kr including VAT. The fixed price covers the work and materials described in attachments 1 and 3. Additional payment can only be claimed for changes approved in writing or other price additions that follow from the agreement and applicable law.
Price estimate
A price estimate is an estimate, not a fixed price. Under the Consumer Craftsman Services Act, the price should normally not exceed the estimate significantly - and not by more than 15 percent - unless otherwise expressly agreed or the customer has approved additions.
Example:
The expected total price is [amount] kr including VAT. The amount is a price estimate under the Consumer Craftsman Services Act. The tradesperson must give written notice if circumstances arise that may affect the estimate.
Hourly rate
For work by the hour, the contract should state:
- Hourly rate including VAT
- Hourly rate for apprentices or assistants
- How hours are recorded
- Expected number of hours
- Whether travel time is invoiced
- Price for the service vehicle
- Minimum billing
- Mark-up on materials
- Price for administration
- When the customer receives timesheets
- A cost ceiling that requires new approval
Example:
The work is invoiced at [amount] kr per hour including VAT. The tradesperson sends a weekly timesheet. If the expected total price exceeds [amount] kr, the work must be stopped until the customer has approved further work in writing.
Ready to find a tradesperson?
Describe your job, compare quotes and pay securely through Fikso.
Free to use · No hidden fees · Payout only after approval
9. Total price and other costs
The contract should show the total amount the customer is expected to pay.
Clarify whether the following are included:
- VAT
- Call-out
- Travel time
- Service vehicle
- Parking
- Toll charges
- Transport of materials
- Tool hire
- Scaffolding
- Lift
- Waste container
- Waste fees
- Cleaning
- Subcontractors
- Application fees
- Technical design
- Documentation
If certain costs cannot be determined in advance, the contract should explain how they are calculated and whether an upper limit applies.
10. Start and completion
The contract should have specific dates.
Include:
- Start date
- Expected completion
- Key milestones
- Working hours
- Planned breaks
- Delivery time for materials
- Deadlines for the customer's product choices
- Deadlines for other trades
- How changes to the schedule are notified
Avoid wording such as "start as soon as possible" or "finished as agreed".
A clearer wording is:
The work starts no later than [date] and must be completed no later than [date], subject to changes approved in writing and documented circumstances outside the tradesperson's control.
Clear deadlines are important if you later need to make a claim because of delay. The Consumer Council points out that it becomes harder to establish a delay if the parties have not agreed when the work is to be finished. See the Consumer Council's guidance on a delayed tradesperson.
11. Delay and daily penalties
In the event of delay, the customer may under the Consumer Craftsman Services Act, among other things, have the right to:
- Withhold payment
- Demand that the service be performed
- Terminate the agreement if the conditions are met
- Claim compensation for documented financial loss
For ordinary renovation and refurbishment jobs, a daily penalty for delay (dagmulkt) does not follow automatically from the Consumer Craftsman Services Act. A daily penalty must therefore be agreed in advance if it is to apply.
The contract can, for example, state:
- The amount per calendar day or working day
- When the daily penalty starts to run
- Which delays the tradesperson is responsible for
- The maximum total amount
- How extensions of the deadline are to be notified
- How delays caused by the customer are handled
Example:
If completion is delayed by circumstances the tradesperson is responsible for, an agreed daily penalty of [amount] kr per calendar day is payable, limited to [maximum amount or percentage]. The daily penalty does not apply where an extension of the deadline has been approved in writing.
It is a good idea to use a recognised standard contract if a daily penalty is to be included.
12. Payment plan
The payment plan should follow documented progress, not just calendar dates.
A plan can, for example, be linked to:
- Ordering and delivery of special materials
- Completed demolition
- Completed hidden construction
- Completed technical installations
- Completed surfaces
- Final inspection and documentation
The contract should describe:
- The amount of each payment
- Which milestone triggers the payment
- Which documentation is required
- Invoice deadline
- Payment deadline
- How disputed amounts are handled
- When the final amount can be paid out
A large advance should be justified by documented costs, for example specially ordered materials.
If the time of payment has not been agreed, the starting point under the Consumer Craftsman Services Act is that payment is made when the tradesperson demands it after the service has been performed. For large projects it is therefore better to agree a clear payment plan.
13. Secure payment
The contract should state how payment is to be made and who the payee is.
Check that:
- The payee matches the contracting party
- The organisation number is on the invoice
- The invoice is itemised
- Changes are shown separately
- The payment can be documented
- The full amount is not paid out before the work starts
- The final amount is linked to inspection and documentation
Fikso has been developed to make paying for services safer. The customer secures the payment before the work starts, and the money is paid out in line with the agreed process.
If a disagreement arises, the payment can be withheld while the parties' documentation is assessed. The agreement should refer to the applicable payment and dispute terms if the job is carried out via Fikso.
A payment solution does not replace the description of the work. What is to be delivered and when the money can be paid out must still be clearly agreed.
14. Additional work and changes
Additional work is one of the most common causes of conflict.
The Consumer Craftsman Services Act has rules on additional work. If the tradesperson discovers a need for work outside the job that it would be practical to carry out at the same time, the tradesperson must as a general rule contact the customer.
The contract should nevertheless have a clear change procedure.
A change order should include:
- Number and date
- Description of the change
- The reason for the change
- Photos or other documentation
- Price for labour
- Price for materials
- Consequences for the schedule
- Any consequences for other trades
- The customer's written approval
Example:
Changes and additional work costing more than [amount] kr must be approved in writing by the customer before the work is carried out. The change order must show the price and any change to the completion date.
Such a threshold should not be interpreted as meaning that the tradesperson is free to carry out all additions below the limit. The purpose is to establish a practical written procedure. The rules of the Act may still apply.
15. Hidden and unforeseen conditions
During a renovation, conditions may come to light that were not visible during the site inspection:
- Rot
- Damp
- Asbestos
- Uneven structures
- Missing insulation
- Illegal electrical installations
- Old or damaged pipes
- Faults in load-bearing structures
- Previous work without documentation
The contract should describe what happens if such conditions are discovered.
Example:
If the tradesperson discovers hidden conditions that may affect price, quality or progress, work on the affected part must be stopped as far as is prudent. The customer must be notified in writing and receive documentation, a proposed solution, the price and the consequences for the schedule before further work is approved.
It should also state who pays for investigations, a surveyor or other expert assistance.
16. The customer's responsibilities
The contract should also describe the customer's obligations.
These may include responsibility for:
- Access to the home
- Moving furniture and belongings
- Electricity and water
- Parking
- Approval from the co-ownership association or housing cooperative
- Product choices within set deadlines
- Delivery of materials bought by the customer
- Information about known damage
- Information about previous work
- Access to drawings and documentation
- Payment according to the agreed milestones
If the customer does not fulfil their obligations, this can affect price and progress. The tradesperson should document the consequence and give notice before claiming additional payment or an extension of the deadline.
17. Applications and public permits
The contract should explain who checks whether the project requires an application.
Clarify:
- Who checks the zoning plan
- Who prepares the drawings
- Who sends the neighbour notification
- Who is the responsible applicant
- Who does the technical design
- Who carries out work that requires an application
- Who pays the municipal fees
- Who applies for the certificate of completion
- Who registers the completed works
Do not settle for the wording "the tradesperson sorts out the paperwork". The tasks and costs should be specified.
The Norwegian Building Authority (Direktoratet for byggkvalitet) has guidance on work on existing buildings and which works may require an application.
18. Subcontractors and other trades
The contract should state whether the business may use subcontractors.
Include:
- Which trades are subcontracted
- Which businesses are to be used
- Who coordinates them
- Who checks registration and qualifications
- Who invoices the customer
- Who is responsible in the event of faults
- Who collects the documentation
For electrical work, the business carrying out the work must be registered with active status in the Register of Electrical Contractors (Elvirksomhetsregisteret). You can check this with the Norwegian Directorate for Civil Protection, DSB.
The contract should not give the main business an unclear right to transfer the entire job to unknown parties without the customer being informed.
19. Quality requirements and professional workmanship
The work must be carried out in a professional manner. The contract can make the quality requirements more specific.
It can, for example, refer to:
- The manufacturer's installation instructions
- Drawings and descriptions
- Relevant parts of the Building Technical Regulations (byggteknisk forskrift)
- Agreed industry standards
- Tolerances
- Surface quality
- Falls and positioning
- Sound or fire requirements
- Chosen product ranges
- Approved sample area or reference
Avoid writing that "high quality" is to be delivered without defining what that means.
For visible work, it can be useful to approve a sample area, a colour sample or a detail solution before the rest is carried out.
20. Documentation during the work
The contract should require documentation before structures are closed up.
This may include photos of:
- Pipe runs
- Electrical cable runs
- Insulation
- Membrane
- Falls in wet rooms
- Reinforcements in walls
- Foundations
- Damp proofing
- Fire stopping
- Hidden repairs
Agree:
- What is to be photographed
- When the photos are to be taken
- Who stores the documentation
- How the customer gets access
- Whether a milestone must be approved before the work is closed up
Photos are not always sufficient professional documentation, but they can be an important supplement.
21. Final documentation
The contract should include a separate list of what is to be delivered when the project is finished.
This may include:
- Invoices and payment overview
- Product and material list
- Colour codes
- Maintenance instructions
- FDV documentation (management, operation and maintenance)
- Photos of hidden structures
- Declaration of conformity for electrical work
- Circuit directory and final inspection
- Documentation of the membrane
- Documentation of plumbing work
- Guarantees
- Drawings
- Approved change orders
- Municipal decisions
- Certificate of completion
- Documentation for the home file (boligmappen)
It should state that the final documentation is part of the delivery, and preferably that part of the final payment only falls due when the documentation has been received.
22. Final inspection and handover
Before the final payment, the customer and the tradesperson should carry out a joint inspection.
The contract should describe:
- When the inspection is to take place
- Who takes part
- How faults are recorded
- Deadline for rectification
- Whether minor faults prevent handover
- When the risk for the work passes
- When the final invoice can be sent
- When the project is considered completed
Draw up a written record.
The record can include:
- Completed work
- Remaining work
- Recorded faults
- Deadline for rectification
- Missing documentation
- Any amount withheld
- Date and signature
An oral walkthrough is harder to document afterwards.
23. Faults, defects and complaints
The contract can explain how the customer is to report faults, but normally cannot limit statutory consumer rights.
For work on real property, the Consumer Council states that the complaint period can be five years. The customer must still complain as soon as possible after the fault was discovered or should have been discovered.
In the event of a defect, the customer may, depending on the circumstances, among other things:
- Withhold the necessary payment
- Demand that the tradesperson rectifies the defect
- Claim a price reduction if the defect is not rectified
- Terminate the agreement if the conditions are met
- Claim compensation for financial loss
The tradesperson normally has both the right and the duty to attempt to rectify the defect. The customer should therefore not immediately engage another business without first notifying the original tradesperson and giving them a reasonable opportunity to investigate and rectify.
Read more at the Consumer Council.
24. Insurance and liability for damage
For larger projects, the contract should describe the tradesperson's insurance and liability.
Ask for information about:
- Liability insurance
- Which business the insurance applies to
- What the insurance covers
- Any limitations
- Liability for damage to the home
- Liability for damage to the neighbour's property
- Liability for water damage, fire or other incidents
- The customer's duty to notify their own insurance company
Insurance does not replace the tradesperson's contractual liability, but can be of great practical importance if extensive damage occurs.
25. Cancellation and stopping the project
The contract should explain what happens if the customer cancels all or part of the work.
Clarify:
- How cancellation is to be notified
- Payment for work already carried out
- Costs for materials already ordered
- Cancellation fees from suppliers
- Handling of special-order products
- Documented financial loss
- Securing and clearing the site
- Handover of materials and documentation
The Consumer Craftsman Services Act has rules on cancellation. A contract should therefore not set arbitrary fees unrelated to the agreement and the financial loss.
26. Disputes and disagreements
The contract should describe an orderly process if the parties disagree.
One possible sequence is:
- The party gives written notice of the problem.
- Both parties submit relevant documentation.
- The tradesperson is given the opportunity to investigate and propose rectification.
- The parties try to agree on a solution and a deadline.
- An independent professional can inspect the work if necessary.
- Disputed payment is withheld to the extent necessary.
- The matter can be taken further to mediation or legal proceedings if the parties cannot agree.
If the job is carried out through Fikso, the contract can refer to the platform's applicable process for documentation, assessment and handling of payment in the event of a disagreement.
Such a process should not be described in a way that removes the parties' mandatory rights under the law or the right to take the matter further.
Example of a simple contract overview
| Item | What should be filled in |
|---|---|
| Customer | Name, address, telephone and email |
| Tradesperson | Legal name, organisation number and contact person |
| Project | Address and description |
| Scope of work | Detailed list and attachments |
| Exclusions | Work that is not included |
| Materials | Product, quality, quantity and responsibility |
| Pricing model | Fixed price, estimate or hourly rate |
| Total price | Price including VAT |
| Start | Specific date |
| Completion | Specific date |
| Payment | Milestones and amounts |
| Extras | Written change order |
| Documentation | Specific list |
| Final inspection | Date, record and rectification deadline |
| Delay | Notification, extension of the deadline and any daily penalty |
| Dispute | Notification, documentation and further handling |
| Signature | Date and signature of both parties |
Common mistakes in tradesperson contracts
The description of the work is too short
"Kitchen renovation" does not explain who demolishes, installs, paints or coordinates the electrician and plumber.
The materials are not specified
"Parquet included" does not say which parquet, quality or price is included.
The completion date is missing
That makes it harder to establish when the work is actually delayed.
Extras are agreed orally
Oral changes carry a high risk of disagreement about price and content.
Payment follows dates instead of progress
The customer may be obliged to pay even if the work is behind schedule.
Documentation is not agreed
The customer only discovers after the final payment that necessary papers are missing.
Responsibility for subcontractors is unclear
The customer does not know who is to handle faults or delays.
The contract refers to attachments that are not included
Check that all attachments are included and are the correct version before signing.
Checklist before signing the contract
- Both parties are correctly identified.
- The organisation number has been checked.
- The project address is correct.
- The work is described in detail.
- Work that is not included is listed.
- The materials are specified.
- The pricing model is clear.
- The total price includes VAT.
- Transport, waste and other fees are clarified.
- Subcontractors are clarified.
- Responsibility for applications is clarified.
- The start date is stated.
- The completion date is stated.
- Payment follows milestones.
- Changes must be approved in writing.
- The consequences of delay are described.
- The final documentation is listed.
- Final inspection and handover are agreed.
- Insurance and liability have been checked.
- Dispute resolution is described.
- All attachments are included.
- Both parties have signed the same version.
Frequently asked questions about tradesperson contracts
Does a tradesperson contract have to be in writing?
An oral agreement can be binding, but a written contract is far easier to document. The Consumer Council recommends that you always draw up a contract.
Who should draw up the contract?
Both the customer and the tradesperson can propose a contract. The most important thing is that both read, understand and approve the content.
Can the tradesperson use their own contract?
Yes, but the customer should check that the contract gives a balanced and clear picture of the work, price, schedule and responsibilities. Terms that conflict with mandatory consumer rules are not necessarily valid even if the customer has signed.
Is an accepted quote a contract?
A quote that the customer accepts can form a binding agreement. Nevertheless, the parties should gather the quote, the clarifications, the attachments and the payment terms in a clear contract.
What is the difference between a fixed price and a price estimate?
A fixed price is an agreed price for a defined piece of work. A price estimate is an estimate that normally cannot be exceeded significantly, and not by more than 15 percent, unless otherwise expressly agreed or there are approved additions.
Can the tradesperson carry out additional work without approval?
The general rule is that the tradesperson must contact the customer if a need for additional work arises. The Act has some exceptions, including for minor additions and work that cannot be postponed without risk of significant damage.
Should the contract include a daily penalty?
For ordinary renovations, a daily penalty does not follow automatically from the Consumer Craftsman Services Act. It must be agreed if it is to apply. For large projects or a critical completion date, it can be useful.
How much should be paid in advance?
You should normally not pay the full amount before the work starts. A limited advance for documented special materials can be reasonable. The rest should follow progress and documented milestones.
What should be stated about materials?
State the manufacturer, product name, model, quality, quantity and who is responsible for measuring, ordering and complaints.
What do I do if the project becomes more expensive?
Ask for written documentation, an explanation, an updated price and the consequences for the schedule. Do not approve major changes orally only.
What should I receive when the work is finished?
You should receive the agreed final documentation, the invoice, product information, photos, guarantees and relevant professional declarations.
Can I withhold payment?
In the event of delay or a defect, you can, depending on the circumstances, withhold as much as is necessary to secure your claim. The amount should be proportionate to the problem.
How long can I complain?
For work on real property, the complaint period can be five years. You must still complain within a reasonable time after you discovered or should have discovered the fault.
Can a contract remove the right to complain?
A tradesperson normally cannot contract out of the mandatory rights you have as a consumer under the Consumer Craftsman Services Act.
Which contract should be used when building a new home?
When a new home is built, the Housing Construction Act (bustadoppføringslova) applies as a general rule. You should then use a contract developed for that Act, not an ordinary renovation contract.
Conclusion: A good contract begins with a clearly defined job
A tradesperson contract should make it easy to understand what is to be delivered, when it is to be delivered and what the customer is to pay.
The most important points are:
- A detailed description of the work
- A clear pricing model
- Specified materials
- A specific schedule
- Payment according to progress
- Written handling of extras
- Clear quality requirements
- Agreed final documentation
- A joint final inspection
- An orderly process for faults or disagreements
A long contract is not necessarily a good contract. The most important thing is that it is precise, understandable and adapted to the project.
It is a good idea to use a recognised standard contract as a starting point. Then attach the description of the work, the product list, the progress plan and the payment plan.
That gives both the customer and the tradesperson a clear map of the project - before the first wall is opened or the first invoice is sent.
Method and sources
This article is based on Norwegian consumer legislation and guidance from public and established professional sources. The rules must be assessed in each specific case, particularly for large or complex building projects.
Sources used as a basis:
- Lovdata - håndverkertjenesteloven
- Lovdata - bustadoppføringslova
- Forbrukerrådet - bruk av håndverker
- Forbrukerrådet - forsinket håndverker
- Forbrukerrådet - misfornøyd med håndverkeren
- Standard Norge - forbrukerblanketter
- Brønnøysundregistrene - virksomhetsopplysninger
- DSB - Elvirksomhetsregisteret
- Direktoratet for byggkvalitet - arbeid på eksisterende bygg